PURA-OLA Project update July 2025
In End December 2024 i came back to pavones to continue another part of the project.
Last year the roof wasn't finished so i used this year to repair and enforce the big second floor platform, that was build last year as i found out theres errors in the building by the team who build it , as a solution i invited a high level engineer who is incharge of 50 other engineers in the big marina project that is now built in Quepos . He took measurments (Spend 5 h at the project to review it all)and asses the errors and came with solutions through supporting the Americana support for the platform that was already made and the futue stairs that were meant to be open concept .we used big metal tubes from black thick metal of 4 by 6 inches with 3,5 mm thickness to create a frame supported by 4 by 4 inches columns. The roof to the house was made this year the rest will be continued next year .
we welcome to visit the site from time to time to see the progress and hopefully within 2027 we can start the project for visitors .